Luas Maintenance Work

We work 24/7 to keep the LUAS network running

Running the LUAS network for Dublin’s commuters is a team effort. The day-to-day operations and maintenance we carry out to keep Dublin moving involves dedicated teams across the city, working collaboratively and ensuring we maintain the best possible service for the commuters who rely on the LUAS, every day.

What is maintenance?

Maintenance work is essential to the operation of the Luas system and ensures we deliver a safe, reliable tram service to our customers. Our maintenance employees support our operations and project teams by making sure every part of our infrastructure – such as signals and power supplies, or assets such as track and platforms – is maintained and in good working order.

Routine maintenance work such as cleaning of infrastructure, washing of platforms and the track, waste management, inspections of the power supply system and light repairs takes place across the system each day and night of the year.

Planned heavy maintenance such as rail replacement, tamping, grinding and tree cutting takes place mainly at night as they require having no trams running.

Emergency works such as rail repair or overhead cable repair takes place as soon as possible to maintain service continuity. This may happen during the night or day.

We understand maintenance work will have an impact on you and your neighbours and for noisy planned maintenance work we distribute a 'Notice of LUAS Track Works' flyer directly to nearby residents in advance and/or post details of the works on the LUAS website. For emergency works, it may not be possible to distribute a notice before undertaking the work.

At all times we appreciate your patience and understanding.


Planned Works Calendar

PAGE LAST UPDATED: 22/09/2017

See details of areas affected by planned Luas rail works, including the date and time they start and finish, and the type of works being carried out.

Location Dates Times Type
Ashling Hotel Sunday 5th - Monday 6th November From 23:00hrs to 06:30hrs Dip Weld Repair
St James Stop Thursday 2nd - Sunday 5th November From 23:00hrs to 06:30hrs Track Shoulder Repairs
St James Street Thursday 2nd - Sunday 5th November From 23:00hrs to 06:30hrs Dip Joint Weld
St James Street Thursday 2nd - Sunday 5th November From 23:00hrs to 06:30hrs Grinding & Welding
Park Gate Street Friday 29th - Saturday 30th October From 23:00hrs to 06:30hrs Arc Welding
Carrickmines Stop Saturday 28th - Sunday 29th October From 23:00hrs to 06:30hrs Jetting
Jervis Stop Wednesday 25th - Thursday 26th October From 23:00hrs to 06:30hrs Arc Welding
Abbey Stop Tuesday 24th - Wednesday 25th October From 23:00hrs to 06:30hrs Arc Welding
Steevens Lane Monday 23rd - Tuesday 24th October From 23:00hrs to 06:30hrs Arc Welding
Cherrywood - Bridesglen Friday 20th - Sunday 22nd October From 23:00hrs to 06:30hrs Hedge Cutting
Park Gate Street Thursday 19th - Friday 20th October From 23:00hrs to 06:30hrs Dip Weld Repair
Blackhorse Tuesday 17th - Wednesday 18th October From 23:00hrs to 06:30hrs Dip Weld Repair
Beechwood - Dundrum Friday 20th - Monday 16th October From 23:00hrs to 06:30hrs Hedge Cutting
Milltown Friday 6th - Monday 9th October From 23:00hrs to 06:30hrs Grinding Switch Blade
Beechwood Crossover Tuesday 12th - Wednesday 13th September From 23:00hrs to 06:30hrs Arc Welding
Cowper-Milltown & Balally Crossover Monday 11th - Tuesday 12th September From 23:00hrs to 06:30hrs Arc Welding
Park Gate Street Sunday 10th - Monday 11th September From 23:00hrs to 06:30hrs Arc Welding
Fettercairn - Saggart Tuesday 8th - Wednesday 9th August From 23:00hrs to 06:30hrs Grinding
Dundrum - Milltown Friday 4th - Monday 7th August From 23:00hrs to 06:30hrs Hedge Cutting

 

Cleaning of Luas Stops is on-going and is not included in the above information.